Saturday, December 14, 2024
HomeRegional and local newsIndianaI-69 project delayed again: Completion reset to May 31, 2018

I-69 project delayed again: Completion reset to May 31, 2018

The Indiana Finance Authority (IFA) and the Indiana Department of Transportation said on Feb. 13 that a memorandum of understanding has been signed with the I-69 Section 5 developer to assure that four lanes of traffic will open through the greater Bloomington area beginning mid-August and to set a final project completion date of May 31, 2018.

“I directed the IFA to work thoroughly and decisively with the developer to resolve outstanding issues and set a firm completion date for I-69 Section 5, and this MOU reflects their efforts,” Gov. Eric J. Holcomb said in a statement. “We all want this project completed as quickly as possible.”

The revised schedule calls for:

  • Four lanes of traffic, two north bound and two south bound, to be continuously open through the greater Bloomington area beginning on Aug. 15, 2017.
  • Four lanes will be open from Sample Road to Martinsville for student move-in and home
    football and basketball games beginning Aug. 15, 2017.
  • The section north of Sample Road to Martinsville also will open to four lanes of traffic
    continuously no later than March 31, 2018.
  • Completion of Section 5 by May 31, 2018.

“This schedule enables six-lane construction to continue to the new completion date,” said Dan Huge, the IFA’s public finance director. “It also aligns with the necessary funding to cover the milestones we need to achieve to complete the project to the standard and quality the people of the state expect.”

I-69 Development Partners and its design-build contractor, Isolux Corsan, will infuse an
additional $75 million into the project, and forgo any prior relief-event claims with the State and the first annual payment the developer would have received for operating and maintaining the roadway upon full completion.

The state, in turn, will convert its first year payment to the developer for operating and
maintaining the finished road into an additional payment to be made during construction –
making $28 million available to the developer this year and in 2018 to fund completion of the project. This arrangement will not increase the overall cost of the project to the state.

The additional payment will be placed in a trust.

I-69 Development Partners’ bondholders must approve the arrangement. Upon their approval, the I-69 Section 5 public-private agreement between the State and the developer will be amended to make the terms of the arrangement legally binding.

I-69 is one of the largest road-projects under construction in the United States, and currently stretches 80 miles between Evansville and Bloomington. Approximately 40 contractors – many local to Indiana – work on the I-69 Section 5 project, which is funded via private-activity bonds that are the sole responsibility of I-69 Development Partners.

The memorandum of understanding may be found here: http://www.in.gov/ifa/2779.htm.

Local leaders, including Bloomington Mayor John Hamilton, called on the state to take back control of the project, which is being completed through a public-private partnership. It’s funded through private activity bonds, Indiana Public Media reported.

“I appreciate the meeting I had with Governor Holcomb last week, and his phone call to me today to inform us all of the state’s latest decisions,” Hamilton said in a statement. “Another delay means for us another winter and spring of difficult travel, lost productivity and danger. I hope this will be the last of these announcements we receive.”

The project, originally to have been completed in 2016, has been plagued by delays. The new completion date is 18 months later than originally planned.

The public-private partnership hasn’t been without controversy, and the completion date has been pushed back multiple times. The Indianapolis Star reported that “major delays started surfacing in September 2016 when subcontractors walked off the job after not getting paid.”

Isolux Corsan, the lead construction contractor on the Section 5 project, blamed the problem on the Indiana Finance Authority, saying it didn’t receive the proper environmental permits. The delays initially pushed back the completion date from October 2016 to October 2017. Stephanie McFarland, an Indiana Finance Authority spokeswoman, directed questions about specific additional delays to Christian Harper, senior vice president for corporate practice for I-69 Development Partners. When reached for comment, he said he was not immediately able to answer questions.

RELATED ARTICLES
- Advertisment -

Most Popular

Recent Comments